ST PETERS CHURCH MACCLESFIELD

ARCHITECT – GRAHAM HOLLAND
CLIENT – PAROCHIAL CHURCH COUNCIL
FUNDED BY – HERITAGE LOTTERY FUND
CONTRACT SUM – £164’131.74
CONTRACT PERIOD – 22 WEEKS
WORKS COMPLETED IN – 25 WEEKS

WORKS CONSISTED ON THE GRADE II LISTED BUILDING TO ADDRESS A LARGE NUMBER OF HIGH-LEVEL REPAIRS.  REPLACEMENT OF THE EXISTING TOWER ROOF, THE NORTH PITCH OF THE NORTH AISLE AND THE VESTRY WERE STRIPPED, TIMBER REPAIRS CARRIED OUT TO THE ROOF STRUCTURE. 

INSULATION WAS INTRODUCED BETWEEN THE RAFTERS.  NEW LEAD SECRET GUTTERS WERE FORMED AND ROOFS RETILED WITH THE EXISTING TILES.  INTERNAL DECORATION OF THE NORTH AISLE AND VESTRY WAS CARRIED OUT.